Categories
Toxic Custard newsletter transport

Down in the trench station at midnight

(With apologies to The Jam)

While we endure the train replacement buses, work is moving along on the Bentleigh-Mckinnon-Ormond trench.

It’s really impressive to see – I worked out you can see all three bridges from the Brewer overpass; with a zoom lens, that is. (This won’t be the case once the station buildings are constructed.)
Bentleigh/Mckinnon/Ormond level crossing works 5/7/2016
(As always, click the photo to see it larger at Flickr. Once there you can click again to see it zoomed in.)

Works are continuing 24 hours a day. Most of the digging has been completed, and works in the trench itself are proceeding at the three station sites.

First a base level of concrete goes in, a working surface, then a thicker layer is added, in part to weigh down and seal the station, as the new Bentleigh station will be below the water table (the same applies at Mckinnon; Ormond is above the water table).

This view from Tuesday night shows preparation for the thicker concrete layer:
Bentleigh station under construction, July 2016

By Thursday night the first section had been poured:
Bentleigh station under construction, July 2016

But if you think it’s impressive from street level, it’s just amazing inside it.

Thanks to the Level Crossing Removal Authority and local MP Nick Staikos I was lucky enough to take a look inside the trench on Thursday night.

Once wearing PPE (Personal Protective Equipment), to get down there you take one of these stairwells.

Bentleigh station under construction, July 2016

On the bottom of the trench you get a perspective completely different to what you see at street level. It’s amazing to think that just a couple of weeks ago trains were passing through here at ground level.

Here’s a quick video:

800-1000 workers are on the job at any one time doing various tasks, and I was amazed at the level of co-ordination that must go into it.

Bentleigh station under construction, July 2016

Shaun Leane (MLC for Eastern Metro) at Bentleigh station under construction

On top of the thick layer of concrete, ballast and track and platforms will be built. The ballast is apparently being sourced from Deer Park. The supplier is likely to be pretty busy over the next few years with all the level crossing removals going ahead (though ballast won’t be used on the Dandenong line). It’s a reminder that there’s a huge supply chain feeding these projects.

Whatdayamean it’s a month until the next train?!
Me at Bentleigh station under construction - whatdayamean it's another month until the next train?

The rain this week has apparently slowed down the project a little bit, but overall it’s still going well. Construction of the platform at Ormond has commenced, as well as laying of track at the Glenhuntly end.

Naturally we had to pose for a happy snap.
Daniel, Steve, Nick, Shaun. Bentleigh station under construction, July 2016. (Pic: Office of Nick Staikos)

I’m not a construction geek, but it’s all incredibly impressive. I’m told over the 37 days of the big shut down, they will spend $100 million.

The buses this week have been mostly smooth, though there have been some hiccups… it’ll be good when it’s finished.

See also:

By Daniel Bowen

Transport blogger / campaigner and spokesperson for the Public Transport Users Association / professional geek.
Bunurong land, Melbourne, Australia.
Opinions on this blog are all mine.

6 replies on “Down in the trench station at midnight”

What ever happened to the term cutting? That is the proper railway term for what is being built here.

I had an interesting bustitute experience during the week where the bus was not going to stop to pick me up despite standing under the blue tent and the driver became a bit mouthy when I took action to get their attention. When people say bustitution ‘only adds x minutes’ to your journey, get over it etc., they’re ignoring the additional uncertainties that can make a single trip stressful, let alone if you have to do it twice a day with multiple connections. Glad the CD9 will involve minimal bustitution.

Great pictures. You captured the scale very well.
With schools going back this week it will be a real test for the system (strain on replacement buses, commuters using other train lines, such as Sandringham).

I like how you say with a slightly embarrassed undertone, “I’m not a construction geek” even though you are a train geek! :)

I hope they’re making one of those ‘Megastructure’ type TV documentaries about this project. The LXRA’s social media channels show 2 minute snippets but I’d like to go deeper and see what happens behind the scenes to plan and execute such a massive undertaking.

It looks like a big, ugly hole in the ground to me. It keeps the suburbs cut in half, in a worse way than the existing line. I live in Armadale and have to experience a big, ugly hole in the ground and a bisected suburb. Skyrail would be a much better option. What a waste of work and money, having to dig out all that soil and waterproof the cutting with thick concrete. I hope they use an elevated option at all other removals where possible.

Whilst I find it interesting seeing how they build such things, I agree 100% that the trench creates a far bigger barrier to the sides of the suburb than any other option.

I get a headache whenever I see a “no sky rail” pamphlet arguing that elevated rail will divide their community and that they want a trench instead.

Comments are closed.